● Microgrid core equipment PCS and microgrid solutions
Grid-Tied Peak-Shaving Customization
Grid-Tied Peak-Shaving Customization

Grid-Tied Peak-Shaving Customization

grid-tied microgrid engineering targeting demand charges and time-of-use tariffs for factories, industrial parks and retail complexes with high demand charges.

0 products
Peak and off-peak electricity prices with arbitrage revenue
Fig. 1|How the money is made: charge in the valley and shoulder periods, discharge during peak windows, and flatten monthly maximum demand — optimizing energy charges, demand charges and time-of-use spread together.
Grid-tied peak shaving customization · restructuring a two-part electricity bill

Peak shaving customization: one battery, three lines of value

Commercial electricity bills normally combine an energy charge with a demand (capacity) charge, then add critical-peak uplifts. Storage earns its keep three ways: shaving the monthly peak demand, moving energy from expensive to cheap hours, and holding up critical load in milliseconds when the utility dips. Our job is to size power and capacity against your real load shape and local tariff, then write those rules into the EMS as an executable schedule.

  • 20%–40%Typical reduction in billed maximum demand
  • 4–6 yearsStatic payback where tariffs cooperate
  • 1–2 cycles/dayCommon cycling strategy
  • below 20 msSupport during a supply disturbance

1. Where the return comes from

Looking only at the peak/valley spread understates the project; demand control alone misses arbitrage. The three orientations below are rarely equal.

Arbitrage only

Buy low, sell high in your own bill.

  • Fit: wide peak/valley spread, load well aligned with tariff windows
  • Risk: depends on policy, consumes the most battery cycles

Demand control only

Push down the highest 15-minute average.

  • Fit: short sharp peaks (injection moulding, stamping, compressors)
  • Risk: high power, short duration, so capacity utilization stays low

Combined

The optimum for most sites.

  • Same asset shaves demand and discharges in peak hours
  • EMS selects the day's strategy from a load forecast
  • Adds ride-through, avoiding short-interruption losses

2. Six capabilities that decide payback

01

Forecast and track the 15-minute window

Estimate running demand in real time and pre-discharge ahead of a known inrush, rather than reacting after the peak has already been recorded.

02

SOC schedules and reserve floors

Generate separate SOC curves by season and day type and reserve headroom for backup, letting energy arbitrage yield to protection when needed.

03

Anti-backflow and reactive support

Enable anti-backflow where export is contractually forbidden, and provide kVAr to keep the power-factor penalty off your bill.

04

Millisecond transfer: storage as an online UPS

Sensitive lines suffer more from short dips than from long outages. Internal transfer performs below 10 ms, external STS below 20 ms — enough for the vast majority of industrial loads.

05

Coordination with transformer and genset

When the transformer cannot cover a short peak, storage or the genset supplies the difference; where chargers are the cause, storage provides dynamic capacity and defers reinforcement.

06

Data closure

Daily charge/discharge records are kept in billing units so theoretical and actual savings can be reconciled every month and the strategy refined.

3. Keeping the three accounts separate

Demand saving = Δ demand kW × demand charge × 12 months
Δ demand = peak 15-minute average before − target value after
Arbitrage = Σ(peak energy × peak price) − Σ(valley energy × valley price) ÷ system efficiency
Static payback ≈ investment ÷ (annual demand saving + annual arbitrage − annual O&M and losses)

Practical rule — size power (kW) from the peak you intend to remove, size capacity (kWh) from how long you need to sustain it. Most commercial projects land on two to four hours of discharge.

4. Typical configurations

Starting points by transformer size and load character
CustomerTransformerPCS powerStorageMain strategy
Small machining / plastics630–1250 kVA250–500 kW500 kWh–1 MWhDemand control first
Medium factory1.6–2.5 MVA500 kW–1 MW1–2 MWhDemand plus arbitrage
Campus / multi-building4–10 MVA1–3 MW2–6 MWhMulti-transformer coordination
Site with chargingAs metered peak500 kW–2 MW1–4 MWhDynamic capacity plus managed charging

5. Recommended platforms

6. How we run the project

  1. Tariff analysis

    Collect twelve months of bills and split energy, demand, power-factor and time-of-use components.

  2. Load analytics

    Read the 15-minute curve, identify what creates peaks and when.

  3. Strategy and sizing

    Choose the strategy mix, then compare two or three power/capacity options with payback.

  4. Integration design

    Connection point, cable routes, cabinet placement, fire provisions.

  5. Install and commission

    Full FAT, grid-synchronisation tests and protection settings review.

  6. Operation tuning

    Calibrate against the first real bill, then review quarterly.

7. Sites in service

1.5 MW microgrid at an injection-moulding plant in Cambodia
1.5 MW plastics plant: demand shaving plus line continuity
Core solution for small and medium factories
Factory sites: compact integrated cabinet footprint
Rooftop PV campus with night-time energy management
Campus: rooftop PV and storage working together
PV self-consumption and storage ratio
Self-consumption: raising the share you use yourself

8. Frequently asked

Our bills are unreadable — where do we start?

Send twelve months of PDF bills. We separate demand, energy, power-factor and time-of-use components, then show exactly how much is addressable.

How do we avoid buying capacity we never use?

Power follows the surge you need to remove, capacity follows how long you need to sustain the discharge. Two to four hours covers most commercial cases; extreme short spikes justify high power with small capacity.

Will it interfere with production?

The system parallels the bus, so only a short planned shutdown is needed to connect. In operation the EMS runs automatically and a bypass is available at any time.

Can it double as backup power?

Yes. We reserve emergency SOC for critical loads and pair it with an STS or internal transfer, giving short-interruption continuity proportional to the reserved energy.

Send twelve months of bills and load data

We will break down your tariff and return viable power/capacity options with a static payback calculation.

Request a peak shaving proposal

No products in this category yet — product series are being published. Enquire for the full range.